Hide Assignment Information Instructions AC 2 1 2 Assignment # 5 Percentage of Completion The Kenny Construction Co . has been contracted to construct a

Hide Assignment Information
Instructions
AC 212
Assignment #5
Percentage of Completion
The Kenny Construction Co. has been contracted to construct a bridge for $3,000,000 at an estimated cost of $2,000,000. The contract period begins on Jan. 1,2012 and ends on Dec. 312014. The following data pertains to the project:
202220232024
Costs to date: $1,000,000 $2,000,000 $2,500,000
Estimated costs to complete: $1,000,000 $500,00 $0
Required:
Calculate the percentage of completion for each year.
Calculate the amount of revenue and gross profit to be recognized each year.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting The Cornerstone of Business Decision Making

Authors: Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger

7th edition

978-1337116008, 1337116009, 1337115770, 978-1337516150, 1337516155, 978-1337115773

More Books

Students also viewed these Accounting questions

Question

How does the concept of hegemony relate to culture?

Answered: 1 week ago