High-End Contractors won a contract to build a new business school worth a total of $45,000,000. The company initially estimates that the total cost for

High-End Contractors won a contract to build a new business school worth a total of $45,000,000. The company initially estimates that the total cost for building the school is $34,400,000 and that it will take 4 years to complete. However, just prior to the preparation of the financial statements for Year 2, the company revises the cost estimate to $37,000,000. 

Information concerning actual costs for years 1 & 2 are provided below.

Year 1

Year 2

Costs incurred during the year

$10,600,000

$15,400,000

How much revenue should High-End recognize during Year 1 & Year 2 if High-End uses the percentage of completion method?

Step by Step Solution

3.48 Rating (158 Votes )

There are 3 Steps involved in it

Step: 1

Lets determine the revenue that HighEnd should recognize during Year 1 and Year 2 ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Intermediate Accounting

Authors: Kin Lo, George Fisher

Volume 1, 1st Edition

132612119, 978-0132612111

More Books

Students also viewed these Accounting questions