Highland Company produces a lightweight backpack that is popular with college students. Standard variable costs relating to a single backpack are given below: Standard Quantity

Highland Company produces a lightweight backpack that is popular with college students. Standard variable costs relating to a single backpack are given below:

Standard Quantity or Hours Standard Price or Rate Standard Cost
Direct materials ? $ 6.00 per yard $ ?
Direct labor ? ? ?
Variable manufacturing overhead ? $ 2 per direct labor-hour ?
Total standard cost per unit $ ?

Overhead is applied to production on the basis of direct labor-hours. During March, 800 backpacks were manufactured and sold. Selected information relating to the months production is given below:

Materials Used Direct Labor Variable Manufacturing Overhead
Total standard cost allowed* $ 19,200 $ 9,200 $ 1,600
Actual costs incurred $ 11,100 ? $ 4,740
Materials price variance ?
Materials quantity variance $ 3,000 U
Labor rate variance ?
Labor efficiency variance ?
Variable overhead rate variance ?
Variable overhead efficiency variance ?

*For the month's production.

The following additional information is available for Marchs production:

Actual direct labor-hours 1,200
Difference between standard and actual cost per backpack produced during March $ 0.15 F

Required:

Hint: It may be helpful to complete a general model diagram for direct materials, direct labor, and variable manufacturing overhead before attempting to answer any of the requirements.

1. What is the standard cost of a single backpack?

2. What was the actual cost per backpack produced during March?

3. How many yards of material are required at standard per backpack?

4. What was the materials price variance for March if there were no beginning or ending inventories of materials?

5. What is the standard direct labor rate per hour?

6. What was the labor rate variance for March? The labor efficiency variance?

7. What was the variable overhead rate variance for March? The variable overhead efficiency variance?

8. Prepare a standard cost card for one backpack

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

No Nonsense Project Auditing A Practical Guide For The PMO

Authors: Lisa Nash

1st Edition

0993403522, 978-0993403521

More Books

Students also viewed these Accounting questions