Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Highway Project Task: Build 6 0 miles of highway over a period of one year. Budget Data: 5 miles per month at $ 5 0
Highway Project
Task:
Build miles of highway over a period of one year.
Budget Data:
miles per month at $ per mile.
Assumptions:
Planned linear accomplishment of work.
All work is measurable except Program ManagementSupport which is LOE.
No work in process at end of month.
Latest Performance Reports:
See the Monthly Performance Data Table and Integrated Program Management Report IPMR for
Month that follow this page.
Calculate the:
Schedule Variance Percentage SV
Cost Variance Percentage CV
Cost Performance Index Efficiency
Cost Performance Index Productivity
Schedule Performance Index SPI
Months ahead or behind schedule
Percent Complete
Percent Spent
To Complete Performance Index TCPI
Independent Estimate at Completion IEAC
Estimated Completion Date in monthsECD
Average Performance Rate Required to achieve the ECD
Section Eamed Value
Note : Reference the Earned Value Analysis Formulas section in Section for details on how to calculate the items listed above. ect data before the IPMDAR Contract Performance Data customer. The two DIDs have similar data requirements.
In addition:
Based on the IPMR data, what type of subcontract is used for the materials cement steel rods etc. Cost Plus, Time and Materials, or Firm Fixed Price?
Where multiple formulas are provided to calculate a data element, select what you consider to be the most likely outcome or most accurate indicator and be prepared to support your selection,
Using the IMPR for month and the IPMR DID extract, be prepared to discuss the contractor's best, worst, and most likely estimated cost at completion. Use your analysis to support your po sition.
Highway IPMR Progress Months Through
In millions of Dollars
tableMonthCurrent,Average,,BudgettableEarnedValueActuals,Budget,tableEarnedValueActuals,Budget,tableEarnedValue
Budget at Completion $
Estimate at Completion $
Estimated Completion Date Month months late
Note: Budget is based on a plan of miles per month at $ per mile miles $ per mile $Budget
Status is based on the number of miles completed times the budget value of $ per mile.
Example: In month seven, miles were completed. miles $ per mile $Earned ValueClassiflcation when FWed inEARED VALUE ANALYSIS FORMULAS
to hapter for explanations of these formulas.
variances
cost Variance ACWP
is favorable underrun
is unfavorable overrun
schedule Variance
is favorable ahead of schedule
is unfavorable behind schedule
variance at Completion BACEAC
VAC is an underrun
VAC is an overrun
Variance Percentages
cost Variance
Schedule Variance Material Variances
Price Variance Unit Price Unit Price
Variance at Completion
Labor Variances
Rate Variance Rate Rate
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started