Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Highway Project Task: Build 6 0 miles of highway over a period of one year. Budget Data: 5 miles per month at $ 5 0

Highway Project
Task:
Build 60 miles of highway over a period of one year.
Budget Data:
5 miles per month at $500,000 per mile.
Assumptions:
Planned linear accomplishment of work.
All work is measurable except Program Management/Support, which is LOE.
No work in process at end of month.
Latest Performance Reports:
See the Monthly Performance Data Table and Integrated Program Management Report (IPMR) for
Month 7 that follow this page.
Calculate the:
Schedule Variance Percentage (SV%)
Cost Variance Percentage (CV%)
Cost Performance Index - Efficiency )E
Cost Performance Index - Productivity )P
Schedule Performance Index (SPI)
Months ahead or behind schedule
Percent Complete
Percent Spent
To Complete Performance Index (TCPI)
Independent Estimate at Completion (IEAC)
Estimated Completion Date (in months)(ECD)
Average Performance Rate Required to achieve the ECD294
Section 4 Eamed Value
Note 1: Reference the Earned Value Analysis Formulas section in Section 6 for details on how to calculate the items listed above. ect data before the IPMDAR Contract Performance Data customer. The two DIDs have similar data requirements.
In addition:
Based on the IPMR data, what type of subcontract is used for the materials (cement, steel rods etc.)? Cost Plus, Time and Materials, or Firm Fixed Price?
Where multiple formulas are provided to calculate a data element, select what you consider to be the most likely outcome or most accurate indicator and be prepared to support your selection,
Using the IMPR for month 7 and the IPMR DID extract, be prepared to discuss the contractor's best, worst, and most likely estimated cost at completion. Use your analysis to support your po. sition.
Highway IPMR Progress Months 1 Through 7
(In millions of Dollars)
\table[[Month,Current,Average,,],[Budget,\table[[Earned],[Value]],Actuals,Budget,\table[[Earned],[Value]],Actuals,Budget,\table[[Earned],[Value]]],[1,2.5,1.0,1.0,2.5,1.0,1.0,2.5,1.0],[2,2.5,1.5,1.5,5.0,2.5,2.5,2.5,1.3],[3,2.5,2.0,2.25,7.5,4.5,4.75,2.5,1.5],[4,2.5,1.5,1.25,10.0,6.0,6.0,2.5,1.5],[5,2.5,1.5,1.75,12.5,7.5,7.75,2.5,1.5],[6,2.5,2.0,2.25,15.0,9.5,10.0,2.5,1.6],[7,2.5,4.0,4.5,17.5,13.5,14.5,2.5,1.93]]
Budget at Completion =$30M
Estimate at Completion =$30.5M
Estimated Completion Date = Month 15(3 months late)
Note: Budget is based on a plan of 5 miles per month at $500,000 per mile 5 miles $500,000 per mile =$2,500,000(Budget)
Status is based on the number of miles completed times the budget value of $500,000 per mile.
Example: In month seven, 8 miles were completed. 8 miles $500,000 per mile =$4,000,000(Earned Value)Classiflcation (when FWed in)EARED VALUE ANALYSIS FORMULAS
Refel to C hapter 13 for explanations of these formulas.
variances
cost Variance (CV)=EV-AC=BCWP-ACWP
CV>0 is favorable (underrun)
C0 is unfavorable (overrun)
schedule Variance (SV)=EV-PV=BCWP-BCWS
SV>0 is favorable (ahead of schedule)
SV0 is unfavorable (behind schedule)
variance at Completion (VAC)=BAC-EAC
VAC>0 is an underrun
VAC0 is an overrun
Variance Percentages
cost Variance %=CVEV100=CVBCWP100
Schedule Variance %=SVPV100=SVBCWS100Material Variances
Price Variance Unit Price -AC Unit Price
Variance at Completion %=VACBAC100
Labor Variances
Rate Variance Rate -AC Rate
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Mind Management Not Time Management

Authors: David Kadavy

1st Edition

0578733692, 978-0578733692

More Books

Students also viewed these General Management questions