Question
1 Approved Answer
Hint: Answer is NOT 1 or 6. The correct diagram is C. inventory on hand. Click the icon to view the product structure. bearing (1
Hint: Answer is NOT 1 or 6. The correct diagram is C.
inventory on hand. Click the icon to view the product structure. bearing (1 week), and shaft ( 1 week). a) Choose the correct time-phased product structure for the bracket. b) In what week do you need to start the castings? The castings need to be started in week 6 (enter your response as a whole number)Step by Step Solution