Holiday Laboratories purchased a high-speed industrial centrifuge at a cost of $480,000. Shipping costs totaled $18,000. Foundation work to house the centrifuge cost $7,100. An
Holiday Laboratories purchased a high-speed industrial centrifuge at a cost of $480,000. Shipping costs totaled $18,000. Foundation work to house the centrifuge cost $7,100. An additional water line had to be run to the equipment at a cost of $2,800. Labor and testing costs totaled $5,900. Materials used up in testing cost $2,000. The capitalized cost is:
Multiple Choice
-
$515,200.
-
$507,900.
-
$498,000.
-
$515,800.