Question
1 Approved Answer
Hours per unit Materials per unit $ Volumes (units) Labour Hours Machine Hours Product X 0.5 1 16 600 Product Y 1.5 1 10 1,300
Hours per unit
Materials per unit
$
Volumes
(units)
Labour
Hours
Machine Hours
Product X
0.5
1
16
600
Product Y
1.5
1
10
1,300
Product Z
1
2
20
7,000
Direct labour cost $7 per hour and production overheads are absorbed on a machine hour basis. The rate for the period is $25 per machine hour.
How can we calculate the cost per unit using Traditional
Step by Step Solution
There are 3 Steps involved in it
Step: 1