Question
1 Approved Answer
How is Earned Value calculated? How is Earned Value calculated? Billable value of work installed up to today Cost of the work installed divided by
How is Earned Value calculated? How is Earned Value calculated? Billable value of work installed up to today Cost of the work installed divided by time elapsed The value of the work that should have been installed according to the schedule What it cost the contractor to install the works up to today