Question

1 Approved Answer

How to get the answer for 2022 and show me the detail, please? thanks In 2021. the Westgate Construction Company entered into a contract to

How to get the answer for 2022 and show me the detail, please? thanks

image text in transcribed
In 2021. the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2821 2322 2323 Cost incurred during the year- $2,188,888 $3,158,888 $2,475,888 Estimated costs to complete as at year-end 5,488,888 2,258,888 8 Billings during the year' 2,158,888 3,188,888 4,758,888 Cash collections during the year- 1,875,888 3,188,888 5,825,888 Westgate recognizes revenue over time according to percentage of completion. 3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. (Do not round intermediate calculations.) Current assets: _ Accounts receivable -_ Construction in progress _-| 955: Billings Costs and prot in excess of billings 650,000 Current liabilities

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Mathematical Statistics With Applications In R

Authors: Chris P. Tsokos, K.M. Ramachandran

2nd Edition

124171133, 978-0124171138

Students also viewed these Accounting questions

Question

What are variable, fixed, and mixed costs?

Answered: 1 week ago

Question

gpt 3 0 9 . .

Answered: 1 week ago