Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be average. However the CFO

Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results:

Economic Scenario Probability of Outcome NPV
Recession 0.05 - $68 million
Below average 0.20 - $10 million
Average 0.50 12 million
Above average 0.20 24 million
Boom 0.05 40 million

Calculate the project's expected NPV, standard deviation, and coefficient of variation. Round your answers to two decimal places. Enter your answers for the project's expected NPV and standard deviation in millions. For example, an answer of $13,000,000 should be entered as 13.

E(NPV) =
NPV =
CV =

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

QFinance The Ultimate Resource

Authors: Various Authors

1st Edition

1849300003, 978-1849300001

More Books

Students also viewed these Finance questions

Question

Describe the linkages between HRM and strategy formulation. page 74

Answered: 1 week ago

Question

Identify approaches to improving retention rates.

Answered: 1 week ago