Huang industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be average. However, the CPO
Huang industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average". However, the CPO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results: ** results are in the attachment**
Calculate the projects expected NPV, standard deviation, and coefficient of variation.