Question
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be average. However, the CFO
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results:
Economic Scenario | Probability of Outcome | NPV |
Recession | 0.05 | ($48 million) |
Below average | 0.20 | (16 million) |
Average | 0.50 | 12 million |
Above average | 0.20 | 24 million |
Boom | 0.05 | 28 million |
Calculate the project's expected NPV, standard deviation, and coefficient of variation. Round your answers to two decimal places. Enter your answers for the project's expected NPV and standard deviation in millions. For example, an answer of $13,000,000 should be entered as 13.
E(NPV) | = $ million |
?NPV | = $ million |
CV | = |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started