Huzaifas company employed several maintenance engineer to keep the equipment running in peak condition. Over the past eight months , Huzaifas company incurred the following
Huzaifas company employed several maintenance engineer to keep the equipment running in peak condition. Over the past eight months , Huzaifas company incurred the following maintenance cost. Plany activity is best measured by direct labor hours.
Months | Direct labor hours | Maintenance cost |
January | 1,700 | $14,300 |
February | 1,900 | $15,200 |
March | 1,800 | $14,200 |
April | 1,600 | $14,000 |
May | 1,500 | $14,300 |
June | 1,300 | $13,000 |
July | 1,100 | $12,600 |
August | 1,400 | $14,200 |
Instructions:
- Using the high-low method. Determine fixed and variable components of maintenance costs.
- Estimate the cost equation in the form of y=a+bx
- What would be the total maintenance cost for 2,000 direct labor hours.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started