Hypothetical Project: Adding Brunch to Al Biernat's Fine-Dining Restaurant Description: Al Biernat's is a fine-dining restaurant in Dallas, TX that has served dinner to the
Hypothetical Project: Adding Brunch to Al Biernat's Fine-Dining Restaurant
Description: Al Biernat's is a fine-dining restaurant in Dallas, TX that has served dinner to the community for many years, serving classically prepared trans-atlantic-inspired cuisine and wishes to begin serving brunch as well; extending service hours while upholding the same fine-dining standards to the patron experience.
Please answer the following questions with the information provided above.
- Staff Assignments
During execution, roles and staffing requirements developed during the planning stage are assigned to the project and are expected to track the number of hours per period they spend on project work. Include the total number of hours this assignee will work during each of the schedule periods (i.e., week 1, week 2, etc)
Fill out one role each and staff assignment for the project manager and 6 other team project members.
2. Staff Development Log
During execution, the project manager plans and executes team development activities which can be logged and tracked.
For 2 selected team members, fill out:
- Development activity
- Type of Activity (training, celebration, teambuilding)
- Participants
- Date of event
3. Work Performance Information (Status Report)
Project status reports are gathered on a regular basis, and the results are evaluated and collated by the project manager. Reports are produced at the level of detail required by the various stakeholders. Fill out the needed information
Status Report for Week Ending in 02/09/2024
Project Start Date: 10/01/2023
Project End Date: 05/01/2024
Percent Complete: Your text here
Project life cycle: Initiation or Planning or Executing or closing?
Short Project Description: Your text here
Significant Accomplishments this period: Your text here
Significant Accomplishments planned for next period: Your text here
Top Issues or Risks Identified: Your text here
Issues requiring Escalation or Management Attention: Your text here
Lessons Learned this period (for project archives): Your text here
4. Executing Procurement Element (Select one major project purchase to answer the following questions.
Agreements
Describes the contract with the seller and the terms of the agreement. A contract is a mutually binding legal agreement. (The type of contract that was used for vendors was the fixed price contract and the type of contract used for the menu is the time and materials contract. The major deliverable to focus on is to Research, develop, and publish the menu)
Describe the Contract with the seller
Your text here
Describe the SOW or deliverables
Your text here
Describe the schedule baseline associated with the purchase or contract.
Your text here
Describe the terms and conditions of the agreement including payment terms, fees, incentives, and penalties
Your text here
What steps will you take to ensure that the Vendor is supplying deliverables of adequate quality?
Your text here
How will you report and resolve variances from acceptance criteria on vendor goods and services?
Your text here
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started