Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

I am having trouble with them There are 3 questions attachedto uploaded file.All three are based on the attached chart. Use the following table to

image text in transcribed

I am having trouble with them

There are 3 questions attachedto uploaded file.All three are based on the attached chart.

image text in transcribed Use the following table to answer question 36-39. Activit Completion y Predecessor time A B C D E F G A A B D, E C, F 5 3 4 6 4 5 6 1) What is the project completion time? A. 22 B. 20 C. 19 D. 17 2) Which activities are on the critical path? A. A, D, F, G B. A, D, E, F C. C, F, A D. D, F, C 3) What is the latest finish time for activity F? A. 12 B. 16 C. 10 D. 9 4) Which activity has the most slack? A. C B. A C. B D. D 5) You have the following results for a given period: Expected completion time of the given project = 44 Variance of project completion time = 5.54 What is the probability of completing the project over 40 days? A. 0.957 B. 0.886 C. 0.896 D. 0.853 1 2

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Derivatives Markets

Authors: Robert L. McDonald

2nd Edition

032128030X, 978-0321280305

More Books

Students also viewed these Finance questions