I am stuck. Month April May June Machine- Hours 52,000 42,000 62,000 72,000 Total Overhead Cost $ 205,640 $ 178,940 $ 232,340 $ 259,040 July

I am stuck. image text in transcribedimage text in transcribedimage text in transcribedimage text in transcribed

Month April May June Machine- Hours 52,000 42,000 62,000 72,000 Total Overhead Cost $ 205,640 $ 178,940 $ 232,340 $ 259,040 July Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 63,000 48,000 67,940 $ 178,940 Nova Company's management wants to break down the maintenance cost into its variable and fixed cost elements. Required: 1. Estimate how much of the $259,040 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $259,040 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.) 2. Using the high-low method, estimate a cost formula for maintenance in the form Y = a + bx. 3. Express the company's total overhead cost in the form Y = a + bx. 4. What total overhead cost would you expect to be incurred at an activity level of 47,000 machine-hours? Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 Estimate how much of the $259,040 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $259,040 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.) (Do not round intermediate calculations.) Maintenance cost in July $ 67,940 Month April May June July Machine- Hours 52,000 42,000 62,000 72,000 Total Overhead Cost $ 205,640 $ 178,940 $ 232,340 $ 259,040 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 63,000 48,000 67,940 $178,940 Nova Company's management wants to break down the maintenance cost into its variable and fixed cost elements. Required: 1. Estimate how much of the $259,040 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $259,040 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.) 2. Using the high-low method, estimate a cost formula for maintenance in the form Y = a +bX. 3. Express the company's total overhead cost in the form Y = a + bx. 4. What total overhead cost would you expect to be incurred at an activity level of 47,000 machine-hours? Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 Using the high-low method, estimate a cost formula for maintenance in the form Y = a + bx. (Do not round your intermediate calculations. Round the "Variable cost per unit" to 2 decimal places.) Y= 76,300) + $ 4.17 Month April May June July Machine- Hours 52,000 42,000 62,000 72,000 Total Overhead Cost $ 205,640 $ 178,940 $ 232,340 $ 259,040 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 63,000 48,000 67,940 $178,940 Nova Company's management wants to break down the maintenance cost into its variable and fixed cost elements. Required: 1. Estimate how much of the $259,040 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $259,040 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.) 2. Using the high-low method, estimate a cost formula for maintenance in the form Y = a +bX. 3. Express the company's total overhead cost in the form Y = a + bx. 4. What total overhead cost would you expect to be incurred at an activity level of 47,000 machine-hours? Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 Express the company's total overhead cost in the form Y = a + bx. (Do not round your intermediate calculations. Round the "Variable cost per unit" to 2 decimal places.) Variable Cost per Machine- Hour Fixed Cost Utilities cost Supervisory salaries cost Maintenance cost Total overhead cost $ 0.00 $ 0 Y = Month April May June July Machine- Hours 52,000 42,000 62,000 72,000 Total Overhead Cost $ 205,640 $ 178,940 $ 232, 340 $ 259,040 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 63,000 48,000 67,940 $178, 940 Nova Company's management wants to break down the maintenance cost into its variable and fixed cost elements. Required: 1. Estimate how much of the $259,040 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $259,040 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.) 2. Using the high-low method, estimate a cost formula for maintenance in the form Y= a +bX. 3. Express the company's total overhead cost in the form Y = a +bX. 4. What total overhead cost would you expect to be incurred at an activity level of 47,000 machine-hours? Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 What total overhead cost would you expect to be incurred at an activity level of 47,000 machine-hours? (Do not round intermediate calculations.) Total overhead cost

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions

Question

Using Language That Works

Answered: 1 week ago

Question

4. Are my sources relevant?

Answered: 1 week ago