I come up with 2 different solution for this problem, however neither seem to be correct becuase when I try and confirm the answer back

I come up with 2 different solution for this problem, however neither seem to be correct becuase when I try and confirm the answer back with known values they don't match. Please respond with details and explain steps so I can see where I went wrong. Thank you in advance. P. S. any answer taken from other sources will be reported as NOT HELPFUL.

image text in transcribed
Our project is running as planned. The following are the latest results: -CPI= 1.3 SPI = 0.9 -PV= 6000 -SV= -1300 Calculate EV and AC option 1 option 2 SV = EV - PV SPC = EV / PV EV = SV + PV EV = SPI X PU = - 1300+ 6000 = 0. 9 x 6000 470 0 $ 5400 CPI = EVAC CPI = FU/AL AC = EV / LPI AL = EV / CPI = 4700 - 1 13 = 5400 7 1,3 2 36 151 38 4153 - 846 SPI = EV = PV SV = EV - PV = 4700 = 6000 - 5400- 6000 7 0. 7833 7 - 600 SPI supposed to = 0 . 9 SV suppose to = - 1300

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Management Science

Authors: Bernard W. Taylor

11th Edition

132751917, 978-0132751919

More Books

Students also viewed these General Management questions