Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

I got 2 different answers for Question #3. Two tutors said the answer is d. One tutor said it's c. I am confused about what

I got 2 different answers for Question #3.

Two tutors said the answer is d. One tutor said it's c.

I am confused about what is correct. They all did not write down the whole calculation to arrive at their answer. So, I cannot decode either. I really need to see the calculation and formula used. So far, all tutors did not provide how the answer was calculated. Because the number was just thrown, although I tried to find a way to get to the answer, I could not. I am at a loss.

Please provide the calculation and formula throughout the process.

Can you please resolve this and help me understand the path to the correct answer?

image text in transcribedimage text in transcribedimage text in transcribedimage text in transcribed
rosemaniebilogs53 Answered 3 days ago d. Explanation: . BAC = $3840000 EV = $1200000 A0 = $1250000 - To find the amount of money needed to complete the project, we need to find the variance. - Variance = EV - AC Variance = 31200000 - $1250000 Variance = $50000 - To nd the total amount of money needed to complete the project, we need to find the total variance. - Total Variance = Variance x {BAG - EV) Total Variance = -$50000 x ($3840000 - $1200000} Total Variance = $15000000 - Total Cost = A0 + Total Variance Total Cost = $1250000 + $15000000 - The cost variance is the difference between the EV and the AC. - The total variance is the cost variance multiplied by the difference between the BAC and the EV. BaronSnail2309 Answered 2 days ago d. $3,000,000 Explanation: Approach to solving the question: . d. $3,000,000 Detailed explanation: . If the cost variance is constant, then it will take an additional $3,000,000 to complete the project. . $3,000,000 = (10,000,000 - 7,000,000) * 1.5 . 10,000,000 = estimated total cost 7,000,000 = actual cost incurred 1.5 = cost variance . Therefore, the answer is d. $3,000,000. . "The variance cost is the difference between a project's" "actual cost and its anticipated cost." . "If the project's" "actual cost is consistently greater than its anticipated cost by same amount," "the actual cost is said to be constant." . In this case, the cost variance is $2,500,000, so it will take an additional $3,000,000 to complete the project (since $2,500,000 + $3,000,000 = $5,500,000, which is the new budgeted cost of the project).3. Assuming that the cool variance la constant, how much more money III It take to complete the project? - 0. $2,800,000 . The project is scheduled to have 8 tower upgrades per month. There are 30 tower upgrades completed in the first 3 months. So. the project is ahead of schedule by 6 tower upgrades. The actual cost of the project is $1.25 million. If the cost variance is constant. the proiect will need $2.8 million to complete. Module 5, Critical Thinking Option #1: Earned Value Analysis for Project Management Institute Exams Given a project with the following characteristics, answer the following questions: You are the project manager of a project to upgrade the generators at cell phone towers. Your project is scheduled to last for 12 months. It is the beginning of month 4 Your crews are to upgrade 8 cell phone towers per month for 12 months Each generator is planned to cost $40.000 which includes equipment, labor, and fueling costs. You have upgraded 30 cell phone towers and your CPI is 0.96. Per month cost estimate = 8*$40,000-$320,000. BAC [budget at completion) = 5320,000*12=$3,840,000 3 months x 8 tower = $320,000*3= $960,000 At the beginning of the 4th month, 30 towers against the scheduled 24 towers completed. EV (earned value) =30*540,000=$1,200,000 CPI-0.96 AC (actual cost) = EV/CPI=$1,200,000/0.96=$1,250,000 (Per-upgrade cost: $1,250,000/3= $41,666.67) 3. Assuming that the cost variance is constant, how much more money will it take to complete the project? a. 52,500,000 b. $2,750,000 C. 52,800,000 d. $3,000,000 What is your reasoning

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Macroeconomics

Authors: David C. Colander

10th edition

1259663043, 1259663048, 978-1259663048

Students also viewed these General Management questions