I got a 60 on this last time and trying to see where i went wrong For Step 1 we are asked to use the
I got a 60 on this last time and trying to see where i went wrong
For Step 1 we are asked to use the Apportion Method to determine the budget for a relocation project
Total Budget = $85,000
- Initial Design Work = 10%
- Ventilation System = 35% (Parts = 20%; Labor = 15%)
- New Racks = 20% (Parts = 15%; Labor = 5%)
- Power Supplies and Cables = 25% (Parts = 15%; Labor = 10%)
- Switchover Ops Checks = 10%
Then in Step 2: we are given the budget and schedule details below and asked to use the Time Phased Budget method to determine the budget. Assuming the "cost of parts" is paid in the first unit of time, and the labor is equally spread out over the units of time.
Total Budget = $85,000
- Initial design Work = 10%
- Ventilation System = 35% (Parts = 20%; labor = 15%)
- New Racks = 20% (Parts = 15%; labor = 5%)
- Power Supplies and Cables = 25% (Parts = 15%; labor = 10%)
- Switchover Ops Checks = 10%
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started