I have completed parts #1, #2, #3. Please Look them over and verify if they are right. Please answer parts #4-9 #1 #2 #3 #4
I have completed parts #1, #2, #3. Please Look them over and verify if they are right.
Please answer parts #4-9
#1
#2
#3
#4 (please answer parts #4-9)
#5
#6
#7
#8
#9
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,840,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2020 2021 $ 438,000 $1,140,000 1,022,000 0 420,000 1,420,000 320,000 1,520,000 Assume that Beavis recognizes revenue upon completion of the project. Required: Prepare all journal entries to record costs, billings, collections, and profit recognition. (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.) Journal entry worksheet Record the entry for costs incurred during the year 2020. Note: Enter debits before credits. Credit Date 2020 General Journal Construction in progress Cash Debit 438,000 438,000 Journal entry worksheet
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started