Question
I have the following information completed What I need is a sketch of a earned value chart for this project: PV = $60,000 EV =
I have the following information completed
What I need is a sketch of a earned value chart for this project:
PV = $60,000 EV = $55,000 AC = $50,000
Cost variance (CV)
CV = EV - AC
CV = 55,000 50,000
= 5,000
Schedule variance (SV)
SV = EV PV
SV = 55,000 - 60,000
= -5,000
Cost performance index (CPI)
CPI = EV / AC
CPI = 55,000 / 50,000
= 1.1 * 100
= 110
Scheduled performance index (SPI)
SPI = EV / PV
CPI = 55,000 / 60,000
= 0.91 * 100
= 91.6%
The cost variance(CV) is positive, so the cost of work is according to plan only
The schedule variance(SV) is negative, so it takes more time than planned to perform work
The Cost performance index(CPI) is greater than 100%, so the project is under budget
According to the calculated values, the project is running under budget, as well as behind schedule
EAC:
The formula to calculate Estimate at Completion(EAC) is:
EAC = BAC / CPI
BAC = 120,000
= 120,000 / 1.1
= 109,090.909
The EAC is less than the planned 120,000, so the project is performing better than planned in terms of the budget
Estimating Time:
The formula to estimate time is:
SPI = Project duration / SPI
= 6months / 91.6
= 6 / 0.91
= 6.59 months
It will take about 6.5 months to finish the project
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started