I have the following information completed What I need is a sketch of a earned value chart for this project: PV = $60,000 EV =

I have the following information completed

What I need is a sketch of a earned value chart for this project:

PV = $60,000 EV = $55,000 AC = $50,000

Cost variance (CV)

CV = EV - AC

CV = 55,000 50,000

= 5,000

Schedule variance (SV)

SV = EV PV

SV = 55,000 - 60,000

= -5,000

Cost performance index (CPI)

CPI = EV / AC

CPI = 55,000 / 50,000

= 1.1 * 100

= 110

Scheduled performance index (SPI)

SPI = EV / PV

CPI = 55,000 / 60,000

= 0.91 * 100

= 91.6%

The cost variance(CV) is positive, so the cost of work is according to plan only

The schedule variance(SV) is negative, so it takes more time than planned to perform work

The Cost performance index(CPI) is greater than 100%, so the project is under budget

According to the calculated values, the project is running under budget, as well as behind schedule

EAC:

The formula to calculate Estimate at Completion(EAC) is:

EAC = BAC / CPI

BAC = 120,000

= 120,000 / 1.1

= 109,090.909

The EAC is less than the planned 120,000, so the project is performing better than planned in terms of the budget

Estimating Time:

The formula to estimate time is:

SPI = Project duration / SPI

= 6months / 91.6

= 6 / 0.91

= 6.59 months

It will take about 6.5 months to finish the project

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Database Systems Design Implementation And Management

Authors: Carlos Coronel, Steven Morris

14th Edition

978-0357673034

More Books

Students also viewed these Databases questions

Question

What are your options besides a rote memory approach?

Answered: 1 week ago