I need answer following this:- Acme Hotels Inc - SCENARIO The schedule will be for upgrading the Reservation System and adding cell phone based services

I need answer following this:-

Acme Hotels Inc - SCENARIO

The schedule will be for upgrading the Reservation System and adding cell phone based services which are critical to providing the "bleasure" travellers and "millennials" what they are looking for to have the most enjoyable time.

The sponsor believes firmly that the resources available to Acme as a powerful multinational hotel chain can offer many more services, including connections and discounts to many local entertainment, attractions and dining places, will sideline AirBnB's impact to the company and, indeed, turn Acme into a growth business once again.

The sponsor has told you that the project schedule must clearly show the deliverables and when they will be delivered. The importance the PM places on these deliverables means you will show completion of these as Milestones.

The sponsor will want to be updated each week and track progress of the delivery according to the Project Schedule. As a result, the Project Schedule is a critical project monitoring tool you will use daily in the project. You have learned that the project schedule depicts the critical path and knowing which activities are on the critical path you can determine what project team members you can support to ensure they complete their work on schedule so the project does not slip.

INFORMATION to CREATE PROJECT SCHEDULE WITH

Duration Start date End date

Predecessors

All are Finish to Start

0 Acme Hotel Project ? Days Mon 11/8/21
1 PHASE 1 ? Days Mon 11/8/21
2 Communication Management Plan 5 days
3 Conduct team planning 1 day
4 Choose communication plan format 1 day
5 Set communication goals 1 day
6 Identify stakeholders 1 day
7 Determine communication channels and frequency 1 day
8 Communication plan complete 0 days
9 Scope Definition 12 days
10 Collect requirement 6 days
11 Define scope inclusion and exclusion 4 days
12 Define acceptance criteria 1 day
13 Determine assumptions and constraints 1 days
14 Project scope defined 0 days
15 Estimate Budget 8 days
16 Estimate costs 5 days
17 Determine contingencies 3 days
18 Project plan sign-off 0 days
19 PHASE 2 ? Days
20 Conduct Need Evaluation 10 days
21 Personnel Recruitment 7.25 days
22 Post job description 1 day
23 Receive resumes 2 days
24 Screen resumes 2 days
25 Conduct interviews 3 days
26 Hire candidates 1 day
27 Assign responsibilities to resources, Intro to team 1 day
28 Responsibilities assigned to team members 0 days
29 PHASE 3 ? Days
30 Evaluate existing processes 3 days
31 Document all existing users & user roles 3 days
32 Reporting and End-User Management 5 days
33 Configure third party Interconnects (Social Media) 2 days
34 PHASE 4 ? Days
35 Brainstorm ideas 1 day
36 Vote on ideas 1 day
37 Consult with graphic designer 2 days
38 Review and approve draft 1 day
39 Finalize and roll out 1 day
40 Idea finalized and Roll-out 0 days
41 PHASE 5 ? Days
42 Design application architecture map 2 days
43 Create functional specifications 6 days
44 Design process models 3 days
45 Determine user interface 7 days
46 Determine technical and platform specifications 8 days
47 Secure user sign-off (legal agreements, Ts&Cs) 1 day
48 User sign-off on legal and Ts&Cs secured 0 days
49 PHASE 6 ? Days
50 Sketch user flow diagram 1 day
51 Validate flow structure 1 day
52 Choose user interface style 1 day
53 Develop Mockup 5 days
54 Mockup validated 0 days
55 Execute code development 16 days
56 Release testing 3 days
57 Perform bug fixes 2 days
58 User interface developed and tested 0 days
59 PHASE 7 ? Days
60 Record result reporting 1 day
61 Perform additional bug fixes 2 days
62 User interface has no bug 0 days
63 PHASE 8 ? Days
64 Record application statistic documentation 3 days
65 Record end user documentation 2 days
66 File documentation 1 day
67 Training 6 days
68 End user training (tutorials) 3 days
69 Develop training 1 day
70 Conduct training 1.5 days
71 Evaluate training 0.5 days
72 Training completed 0 days
73 PHASE 9 ? Days
74 Marketing meeting with consultant 1 day
75 Use branding/logo to develop further marketing ideas 1 day
76 Design brochures, social media, newsletters (e-mails) 5 days
77 Review + sign-off on marketing campaign 1 day
78 Roll out marketing 8 days
79 Marketing implemented 0 days
80 Project completed 0 days

Apply Core Concepts
Project schedule created as Gantt chart
Quality of Work - Understanding Scheduling
Deliverables with Activities shown
Indentation profile as practiced in class- deliverable and indent activities
Predecessors and dependencies shown
F-S correctly shown
Milestones included

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Principles Of Fraud Examination

Authors: Joseph T Wells

3rd Edition

0470646292, 978-0470646298

More Books

Students also viewed these General Management questions

Question

What are system counter-countermeasures?

Answered: 1 week ago