I need help solving the question marks and number 3 Budget, Standard Cost Variances, T-Accounts Kefter Company manufactures external hard drives. At the beginning of

I need help solving the question marks and number 3

Budget, Standard Cost Variances, T-Accounts

Kefter Company manufactures external hard drives. At the beginning of the period, the following plans for production and costs were revealed:

Units to be produced and sold 25,000
Standard cost per unit:
Direct materials $ 10
Direct labor 8
Variable overhead 4
Fixed overhead 3
Total unit cost $ 25

During the year, 24,800 units were produced and sold. The following actual costs were incurred:

Direct materials $263,872
Direct labor 204,352
Variable overhead 107,340
Fixed overhead 73,904

There were no beginning or ending inventories of direct materials. The direct materials price variance was $9,572 unfavorable. In producing the 24,800 units, a total of 12,772 hours were worked, 3 percent more hours than the standard allowed for the actual output. Overhead costs are applied to production using direct labor hours.

Required:

Instructions for parts 1 and 2: If a variance is zero, enter "0" and select "Not applicable" from the drop down box.

1. Prepare a performance report comparing expected costs to actual costs.

Kefter Company Performance Report
Cost Items Actual Costs Budgeted Costs Variance Direction
Direct materials 263,872 248000 158752

Unfavorable

Direct labor 204352 198400 5952

Unfavorable

Variable overhead 107340 99200 8140

Unfavorable

Fixed overhead 73904 75000 -1096

Favorable

649468 620600 28868

Unfavorable

2. Determine the following. If a variance amount is zero, enter "0" and select "Not applicable" from the drop-down list.

a. Direct materials usage variance $6,300

b. Direct labor rate variance 0

c. Direct labor usage variance $5,952

d. Fixed overhead spending and volume variances

Spending variance ?????

Favorable

Volume variance ????

Unfavorable

e. Variable overhead spending and efficiency variances

Variable overhead spending variance ??????

Unfavorable

Variable overhead efficiency variance ??????

Unfavorable

3. Use T-accounts to show the flow of costs through the system. In showing the flow, you do not need to show detailed overhead variances. Show only the over-and underapplied variances for fixed and variable overhead. Record the following transactions in the T-accounts: If an amount is zero, enter "0". Put the letter in T-Accounts..

(a) purchase of materials,

(b) issuance of materials into production,

(c) incurrence of direct labor cost,

(d) application of variable overhead cost to production,

(e) application of fixed overhead cost to production,

(f) transfer of finished goods to finished goods inventory,

(g) sale of goods,

(h) closure of Direct Materials Price Variance account,

(i) closure of Direct Materials Usage Variance account,

(j) closure of Direct Labor Efficiency Variance account,

(k) closure of Variable Overhead Control account, and

(l) closure of Fixed Overhead Control account.

Enter these transactions in the T-accounts in the same order that they are presented here.

T accounts are materials, Work in Process, Finish Goods, DM Price Variance, DM Usage Variance, AP, wage payable, DL Rate Variance, DL efficiency variance, and Variable OH control

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Information Systems Thinking Development And Evaluation

Authors: Robyn L. Raschke, John A. Schatzel

1st Edition

1453396950, 9781453396957

More Books

Students also viewed these Accounting questions

Question

=+23. Advertising strategies EVPI.

Answered: 1 week ago