Question

1 Approved Answer

I need help with a Gantt Chart. I just can't figure it out. Task Name Start Date End Date Duration Organizational Needs Assessment 6/7/2023 6/23/2023

I need help with a Gantt Chart. I just can't figure it out.

Task Name Start Date End Date Duration
Organizational Needs Assessment 6/7/2023 6/23/2023 12d
Identify and hire project team members 6/7/2023 6/12/2023 3d
Define organizational objective 6/12/2023 6/13/2023 1d
Develop a plan for collecting information 6/13/2023 6/14/2023 1.50d
Implement the data gathering plan 6/14/2023 6/21/2023 5d
Interpret and report findings 6/21/2023 6/23/2023 1.50d
Identify Consultants 6/23/2023 7/7/2023 10d
Perform initial screening of applicant pool 6/27/2023 6/30/2023 3d
Interview potential candidates 6/30/2023 7/7/2023 5d
Determine the level of training required 6/23/2023 6/27/2023 2d
Hire Consultants 7/7/2023 7/28/2023 15d
Create a bid package 7/7/2023 7/14/2023 5d
Gather required information from the consultants 7/14/2023 7/21/2023 5d
Negotiate and close contract 7/21/2023 7/28/2023 5d
System Planning 6/27/2023 8/3/2023 27d
Establish system protocols 6/27/2023 6/27/2023 0.50d
Develop implementation plan 7/28/2023 7/31/2023 1d
Develop test plan 7/31/2023 8/1/2023 1d
Develop risk assessment 8/1/2023 8/3/2023 2d
Design / Configure System 8/3/2023 8/31/2023 20d
Configure system for Internet access 8/3/2023 8/10/2023 5d
Configure software 8/10/2023 8/24/2023 10d
Test software 8/24/2023 8/29/2023 3d
Identify necessary hardware 8/29/2023 8/31/2023 2d
Implementation 6/23/2023 12/12/2023 122.50d
Purchase materials required for project 8/31/2023 9/14/2023 10d
Sign contracts for office connectivity 8/31/2023 9/7/2023 5d
Schedule installation of the above items 9/14/2023 9/14/2023 0.50d
Create internet/email usage policy 6/23/2023 7/7/2023 10d
Develop training manual 8/3/2023 8/24/2023 15d
Create a pilot test group 7/7/2023 7/7/2023 0.50d
Install beta cable 9/14/2023 9/15/2023 1d
Install beta hardware 9/15/2023 9/20/2023 3d
Install beta server software 9/20/2023 9/22/2023 2d
Install beta client software 9/22/2023 9/25/2023 1d
Install beta security system 9/22/2023 9/26/2023 2d
Deploy the software for the test group 9/26/2023 9/28/2023 2d
Train the Beta Test Group 9/28/2023 10/2/2023 2d
Monitor the pilot group and system 10/2/2023 10/16/2023 10d
Beta test group post-mortem evaluation 10/16/2023 10/18/2023 2d
Debug and reconfigure system 10/18/2023 10/23/2023 3d
Install cable 10/23/2023 10/25/2023 2d
Install Hardware 10/25/2023 10/30/2023 3d
Install Server Software 10/30/2023 11/1/2023 2d
Install Client Software 11/1/2023 11/3/2023 2d
Install Security System 11/3/2023 11/7/2023 2d
Deploy the software for the company 11/7/2023 11/9/2023 2d
Test Cable 10/25/2023 10/26/2023 1d
Test Hardware 10/30/2023 11/1/2023 2d
Test Server Software 11/1/2023 11/3/2023 2d
Test Client Software 11/3/2023 11/7/2023 2d
Test Security System 11/7/2023 11/9/2023 2d
Train All Users 11/9/2023 11/14/2023 3d
Monitor users 11/14/2023 12/12/2023 20d
Post Evaluation 12/12/2023 12/28/2023 12d
Post implementation evaluation 12/12/2023 12/14/2023 2d
Finalize system documentation 12/14/2023 12/28/2023 10d
Project Management 6/7/2023 12/14/2023 136.50d
Project Management Period 1 6/7/2023 6/20/2023 9d
Project Management Period 2 6/23/2023 7/5/2023 8d
Project Management Period 3 7/7/2023 7/26/2023 13d
Project Management Period 4 7/28/2023 8/1/2023 2d
Project Management Period 5 8/3/2023 8/21/2023 12d
Project Management Period 6 8/24/2023 9/11/2023 12d
Project Management Period 7 9/14/2023 9/21/2023 5d
Project Management Period 8 9/22/2023 9/29/2023 5d
Project Management Period 9 10/2/2023 10/20/2023 14d
Project Management Period 10 10/25/2023 10/30/2023 3d
Project Management Period 11 11/1/2023 11/7/2023 4d
Project Management Period 12 11/9/2023 12/14/2023 25d
Milestones 6/23/2023 12/28/2023 134.50d
Milestone 1 6/23/2023 6/23/2023 0d
Milestone 2 7/7/2023 7/7/2023 0d
Milestone 3 7/28/2023 7/28/2023 0d
Milestone 4 8/3/2023 8/3/2023 0d
Milestone 5 8/24/2023 8/24/2023 0d
Milestone 6 9/14/2023 9/14/2023 0d
Milestone 7 9/22/2023 9/22/2023 0d
Milestone 8 10/2/2023 10/2/2023 0d
Milestone 9 10/25/2023 10/25/2023 0d
Milestone 10 11/1/2023 11/1/2023 0d
Milestone 11 11/9/2023 11/9/2023 0d
Milestone 12 12/28/2023 12/28/2023 0d

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these General Management questions

Question

What made you decide on this subfield of psychology?

Answered: 1 week ago

Question

How appropriate would it be to conduct additional research?

Answered: 1 week ago

Question

Who are credible sources and opinion leaders for this public?

Answered: 1 week ago

Question

How does or how might your organization affect this public?

Answered: 1 week ago