I need help with the mathemathical solving problem. Minimum Cost Schedule ( 2 5 points ) . Information concerning a project is given in the
I need help with the mathemathical solving problem. Minimum Cost Schedule points Information concerning a project is given
in the table below.
Activity Normal
Time
days
Normal
Cost $
Crash
Time
days
Crash Cost
$
Immediate
Predecessors
A
B
C AB
D B
E CD
F E
G E
H G
Indirect project costs amount to $ per day. The company will incur a $ per
day penalty for each day the project lasts beyond day
a What is the projects duration if only normal times are used?
b What is the minimumcost schedule?
c What is the critical path for the minimumcost schedule?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started