Answered step by step
Verified Expert Solution
Question
1 Approved Answer
I need question number 10 solved in the template under it: Contract Amount 42.136 8,200 Code Description 04100 Masonry 05900 Erection 07200 Insulation 07500 Raofing
I need question number 10 solved in the template under it:
Contract Amount 42.136 8,200 Code Description 04100 Masonry 05900 Erection 07200 Insulation 07500 Raofing 08400 Store Fronts 10. Your company has been hired to act as a construction manager for the construction of a bookstore for a fixed fee of $32,000. when the design was 90% complete, you prepared a budget for the project, which is shown in 6,898 09200 Ceramic THe 09300 Acoustical Treatment 09400 Carpet and Vinyl 09800 Paint 5,354 Code Description 01100 01700 Temporary Utilities 01900 Cleanup 03300 Footing and Foundation-Labor 03400 Footing and Foundation Concrete 03450 Concrete Pump 03500 Slab/Fioor-Labor 03600 Slab Floor-Concrete 03900 Rebar 04100 Masonry 05100 Structural Stee 05300 Joist and Deck 05900 Erection 06110 Rough Carpentry 06120 Lumber 07200 Insulaion 07500 Roofing 07700 Roof Specialties 08110 Metal Doors and Frames 08400 Store Fronts 08700 Hardware 09100 Drywall 09200 Ceramic Tile 09300 Acoustical Treatmerit 09400Carpet and Vinyl 09800 Paint Budget 12300 Cabinetry and Countertops 36,00021100 Fire Sprinklers 6,700 22100 Plumbing 4,600 23100 HVAC 3,40026100 Electrical 3,500 31100 Grading and Excavation 1,700 32100 Asphalt 2,100 33100 Sanitary Sewer 6,800 33200 Water Line 23,850 17,825 17,569 FIGURE 4-13 Subcontracts for Problem 10 44,000 11,000 During the buyout, the subcontracts shown in Figure 4-13 were signed and the purchase orders shown in Figure 4-14 were issued. No additional costs are expected for the contracts in Figure 4-13 and the purchase orders in Figure 4-14. A purchase order has been issued for con crete for $115 per cubic yard. This price is 4% below the costs used in the budget. You have a meeting with the project's owner to discuss the financial status of the project. Using the commit ted cost worksheet in Figure 4-1 of the textbook, update the estimated cost at completion and determine if the project is over or under budget. 8,600 500 900 9,000 1,000 2,900 9,500 1,900 7,200 5,500 8,200 500 Toilet & Bath Accessories Cabinetry and Countertops 10800 12300 10,000 21100 Fire Sprinklers 6,700 22100 Plumbing 23100 HVAC 26100 Electrical 31100 Grading and Excavation 32100 32200 Site Concrete Labor 32300 Site Concrete Concrete 32500Landscaping 24,000 23,000 PO Amount 10,250 15,500 6,300 Code Description 17,000 05100 Structural Steel 1,000 05300 Joist and Deck 1,00006120 Lumbe 1,000 07700 Roof Spocialties 1,000 08110 Metal Doors and Frames 1,000 08700 Hardware 945 2,725 33200 Water Line Profit and Overhead TOTAL 32,000 10400 Signage 346,60010800 Toilet & Bath Accessories 965 FIGURE 4-12 Budget for Problem 10 FIGURE 4-14 Purchase Orders for Problem 10 Contract Amount 42.136 8,200 Code Description 04100 Masonry 05900 Erection 07200 Insulation 07500 Raofing 08400 Store Fronts 10. Your company has been hired to act as a construction manager for the construction of a bookstore for a fixed fee of $32,000. when the design was 90% complete, you prepared a budget for the project, which is shown in 6,898 09200 Ceramic THe 09300 Acoustical Treatment 09400 Carpet and Vinyl 09800 Paint 5,354 Code Description 01100 01700 Temporary Utilities 01900 Cleanup 03300 Footing and Foundation-Labor 03400 Footing and Foundation Concrete 03450 Concrete Pump 03500 Slab/Fioor-Labor 03600 Slab Floor-Concrete 03900 Rebar 04100 Masonry 05100 Structural Stee 05300 Joist and Deck 05900 Erection 06110 Rough Carpentry 06120 Lumber 07200 Insulaion 07500 Roofing 07700 Roof Specialties 08110 Metal Doors and Frames 08400 Store Fronts 08700 Hardware 09100 Drywall 09200 Ceramic Tile 09300 Acoustical Treatmerit 09400Carpet and Vinyl 09800 Paint Budget 12300 Cabinetry and Countertops 36,00021100 Fire Sprinklers 6,700 22100 Plumbing 4,600 23100 HVAC 3,40026100 Electrical 3,500 31100 Grading and Excavation 1,700 32100 Asphalt 2,100 33100 Sanitary Sewer 6,800 33200 Water Line 23,850 17,825 17,569 FIGURE 4-13 Subcontracts for Problem 10 44,000 11,000 During the buyout, the subcontracts shown in Figure 4-13 were signed and the purchase orders shown in Figure 4-14 were issued. No additional costs are expected for the contracts in Figure 4-13 and the purchase orders in Figure 4-14. A purchase order has been issued for con crete for $115 per cubic yard. This price is 4% below the costs used in the budget. You have a meeting with the project's owner to discuss the financial status of the project. Using the commit ted cost worksheet in Figure 4-1 of the textbook, update the estimated cost at completion and determine if the project is over or under budget. 8,600 500 900 9,000 1,000 2,900 9,500 1,900 7,200 5,500 8,200 500 Toilet & Bath Accessories Cabinetry and Countertops 10800 12300 10,000 21100 Fire Sprinklers 6,700 22100 Plumbing 23100 HVAC 26100 Electrical 31100 Grading and Excavation 32100 32200 Site Concrete Labor 32300 Site Concrete Concrete 32500Landscaping 24,000 23,000 PO Amount 10,250 15,500 6,300 Code Description 17,000 05100 Structural Steel 1,000 05300 Joist and Deck 1,00006120 Lumbe 1,000 07700 Roof Spocialties 1,000 08110 Metal Doors and Frames 1,000 08700 Hardware 945 2,725 33200 Water Line Profit and Overhead TOTAL 32,000 10400 Signage 346,60010800 Toilet & Bath Accessories 965 FIGURE 4-12 Budget for Problem 10 FIGURE 4-14 Purchase Orders for Problem 10Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started