Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

I need some help with this for cost estimating. will you please provide solutions and as best as can show how you came about it.

I need some help with this for cost estimating. will you please provide solutions and as best as can show how you came about it. Provided is the overhead information and a template below to fill in. All the points to the best answer and a million thanks

1. Use the following information to complete the overhead estimate for a $1.63 Million project with an 11 month schedule:

Job staff superintendent (full time), project manager (1/2 time)

Travel the jobsite is located 30 miles from the main office, the project manager will visit 1/week.

Temporary toilet mobilization and demobilization costs are $100/each.

Temporary lights include $600 for materials and 40 laborer hours.

Temporary heat include lump sum amount of $1200.

Job Office mobilization and demobilization costs are$250/each.

Storage facilities mobilization and demobilization costs are $150/each.

Deliveries allow 4hr/week at rate of laborer and truck costs are equivalent.

Job clean up allow 4hr/week by a laborer.

Janitorial the building is 33,000 SF.

Dump charges assume that you will need 1 dump/3 weeks through out the project. The last month will require 1 dump/week. Each dump costs $400.

Pick up truck the superintendent will have a pick-up truck for his use the entire duration of the project..

Gross receipts tax will cost 0.1% of the total project value.

Photographs are required allow $100/month.

The site perimeter is 1000 lf and fencing will cost $2/lf, and 1 - 20 gate for $1500.

Allow $1500 for safety & 40 carpenter hours.

The bond rate is 0.85%

Allow $2500 for punchlist material and 40 carpenter hours.

Your firm uses the following typical pricing information for your estimates:

Labor rates:

Carpenter $20/hour

Laborer $12/hour (Deliveries are typically made by a laborer.)

Superintendent $30/hour

Project manager $35/hour

Pick up truck for superintendent is charged at $825/mo.

Mileage is paid at $.55/mile.

Job office trailers are rented for $420/month

Storage trailers are rented for $180/month

Temporary toilets are rented for $90/month

Job Sign typical $1550 and 20 carpenter hours.

Janitorial costs (final clean up) allow $.25/sf.

Pump & dewater equipment LS $250, laborer hours 25

Electric set up LS $1500.00

Electric monthly $60/month for first 18 months, $350/month remainder of project

Water set up LS $350, water monthly $100.

Telephone, set up $500, monthly costs $150.

Bottled water, set up & remove LS $75, monthly $60.

Surveys $1200 per day.

Job office furnishings are LS $2500. and there are 40 carpenter hours required to set up the office.

Fax/computer is charged at $60/mo.

Hyster/forklift rental $1050/mo.

Job Duration: Duration 18 months

Finish
LD's
Description Unit Equip/Sub Material Labor
Supervision
Superintendent- full time
Foreman(non-working)
Foreman(Differential)
Project Manager
Job Engineer, clerk, etc
Travel expense, Bridge, Parking(not pick up)
Facilities
Job Office -
Job Office - (furnishings)
Office(mobilization)
Fax/Computer
Toilets
Toilets - mobilization
Temporary Light
Temporary Heat
Storage Facilities
Storage Facilities - mobilization
Job Sign & Installation
Deliveries
Clean Up
Job Clean Up - (3% to 7% Labor
Janitorial
Finish Site Grading(if not in estimate)
Debris, Off Haul, Dump Charges
Equipment(if not in estimate)
Pick Up Truck - including gas
Hyster/Forklift - (job service)
Generator
Pump/Dewater
Table Saw
Scaffold, Planks
Hoist - Manlift
Equipment Transport
Crane
Utilities
Job Service
Electric Set Up(temp. poles, etc; +utility fees
Electric - Monthly
Water - Set Up - -by owner
Water - Monthly-by owner
Telephone - Set Up
Telehone - Monthly
Permanent
Special Assessments/Connnections
Bottled Water
bw SET UP & REMOVE
Fees
Permit/Plan Check -by owner
Business License
Grading Permit
Gross Receipts Tax(0.1% - 0.3%)
Services
Surveys
Concrete Design
Concrete Test
Soil Test
Other Test
Critical Path Schedule (CPM)
Engineering/Design
Photographs
Printing
Legal
QC
Other
Site Conditions
Traffic Flagmen
Temporary Road(including maintenance)
Job Security
Temporary Fence, Barricades
Watchmen
Window Protection
Loss Allowance
Safety
Ladders, Rails, Stairs, Closures, etc.
Insurance
Fire Insurance/Builders Risk(0.12% -0.35%)
Quake
Liquidated Damages
Allow For
Bond
Rate - 0.85%
Allowances
Specified
Punchlist/Closeout
Punchlist Labor/misc
Touch up/etc.
Printing/etc.
Total Job Overhead
Labor, Insurance, Burden
+1% refinery work
-1% if CD for retention
-1/2% if 5% retention
Job Efficiencies
Size, supervision, labor available
distance, job type, public/private
clarity of plans, weather
Escalation(show formula)
Subtotals
BURDEN
$0
TOTAL

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing Fundamentals In A South African Context

Authors: Gerrit Penning, Rika Butler, Pieter Von Wielligh, Frans Prinsloo

2nd Edition

0190749040, 978-0190749040

More Books

Students also viewed these Accounting questions