Question

...
1 Approved Answer

I need to create a full network diagram (using the critical path method that includes both the forward and backward pass information) for the project.

I need to create a full network diagram (using the critical path method that includes both the forward and backward pass information) for the project. please see photo attached

image text in transcribed
WSB Item/Task Dependencies Duration in days A 14 B A 14 C B 42 D A 35 E H 56 F H 28 G A 28 H C, INSPECTION 28 E.F,L,O 14 INSPECTION 35 K H.J.M 21 L K, N 21 M INSPECTION 28 N M 14 O N 28 Inspection B,D,G 14

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Entrepreneurship

Authors: Andrew Zacharakis, William D Bygrave

5th Edition

9781119563099

Students also viewed these General Management questions