I need to create a full network diagram (using the critical path method that includes both the forward and backward pass information) for the project.
I need to create a full network diagram (using the critical path method that includes both the forward and backward pass information) for the project. please see photo attached
WSB Item/Task Dependencies Duration in days A 14 B A 14 C B 42 D A 35 E H 56 F H 28 G A 28 H C, INSPECTION 28 E.F,L,O 14 INSPECTION 35 K H.J.M 21 L K, N 21 M INSPECTION 28 N M 14 O N 28 Inspection B,D,G 14Step by Step Solution