Question
Brooks Software Limited ( BSL ) was formulated and registered on March 1 5 , 2 0 0 0 with the registered office located
Option Modify Customize Option Replace
Project Cost $ Project Cost $
Time Frame months Time Frame months
Brings system to pass global and regulatory standards compliance Brings system to pass global and regulatory standards compliance
new system features new system features
Payback period is three years Payback period is four and a half years
The directors of the credit union have decided to give full autonomy to BSL to make recommendations as to the best suitable option seeing that they are the experts. BSL usually makes recommendations based on the goals and objectives of their client.
Required:
You are the project managers at BSL based on the two options presented to the Credit Union, which option would you recommend and why?
Explain THREE steps in validating the project you have recommended above.
Seeing that BSL makes recommendations based on the goals of their client. Formulate a possible goal for SPCU and discuss the FIVE characteristics of a goal.
Define the scope of the project recommended.
Despite BSL being given full autonomy over the project, explain the importance of the user as part of the team and give two reasons why the user should be involved in the project.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
1 Recommendation of the Best Suitable Option As the project manager at Brooks Software Limited BSL the recommendation would be Option 2 Replace the Existing System This recommendation is based on the ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started