Exercise 1:

Develop the AON and AOA networks based on the following project schedule - how long does it take to completing this project. Draw both AON and AOA networks and identify the critical path.

ID ACTIVITY DUR. (days) Predecessor(s)
1 A 5
2 B 5 1
3 C 5
4 D 5 1
5 E 5 1
6 F 5 3,4
7 G 5 1
8 H 5 5,6,7
9 I 5 6,8

Exercise 2:

Develop the AON networks based on the following project schedule - how long does it take to completing this project. Draw the AON network and identify the critical path.

ID ACTIVITY DUR. (days) Predecessor(s)
1 A 5
2 B 5 1
3 C 5
4 D 5 1
5 E 5 1
6 F 5 3,4
7 G 5 1
8 H 5 2,5
9 I 5 2,5
10 J 5 9
11 K 5 8

Exercise 3:

Develop the AON networks based on the following project schedule - how long does it take to completing this project. Draw the AON network and identify the critical path.

WBS ID Activity Duration Cost Predecessors
1 1 Pool Project
1.1 2 Excavation 5d $6,000
1.2 3 Reinforcing structure 3d $5,900 2
1.3 4 Install piping 4d $3,800 3
1.4 5 Install electrical 3d $3,900 3
1.5 6 Blow pool concrete shell 5d $13,500 5,4
1.6 7 Install decking 5d $6,000 6FS+5d
1.7 8 Install pumps and blower 4d $4,200 7
1.8 9 Install filtration system 2d $3,600 7
1.9 10 Install landscaping 5d $6,000 9, 8
1.1 11 Checkout system 1d $600 10
1.11 12 Final approval 0d $0 11

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

MIS Essentials

Authors: David M Kroenke

1st Edition

0136075606, 9780136075608

More Books

Students also viewed these General Management questions

Question

a sin(2x) x Let f(x)=2x+1 In(be)

Answered: 1 week ago

Question

5. How can I help others in the network achieve their goals?

Answered: 1 week ago