Ice Cool produces two different models of air conditioners. The activities, costs, and cost drivers associated with the production processes follow. Process Activity Budgeted Cost
Ice Cool produces two different models of air conditioners. The activities, costs, and cost drivers associated with the production processes follow.
Process | Activity | Budgeted Cost | Activity Cost Driver | Budgeted Activity Usage |
---|---|---|---|---|
Assembly | Machining | $ 279,000 | Machine hours (MH) | 6,000 |
Setups | 24,000 | Setups | 120 | |
$ 303,000 | ||||
Finishing | Inspecting | $ 210,000 | Inspections | 700 |
Support | Purchasing | $ 135,000 | Purchase orders | 450 |
Additional production information concerning its two models follows.
Units and Activities | Model X | Model Z |
---|---|---|
Units produced | 1,724 | 3,463 |
Machine hours | 1,800 | 4,200 |
Setups | 40 | 80 |
Inspections | 400 | 300 |
Purchase orders | 300 | 150 |
Per Unit | Model X | Model Z |
---|---|---|
Selling price per unit | $ 420 | $ 400 |
Direct materials cost per unit | 100 | 90 |
Direct labor cost per unit | 150 | 160 |
1. Compute the activity rate for each activity using activity-based costing. 2. Using activity-based costing, compute the overhead cost per unit for each model. 3. Compute the total product cost per unit for each model. 4. For each model, compute the gross profit per unit (selling price per unit minus product cost per unit).
Using activity-based costing, compute the overhead cost per unit for each model. (Round "Activity Rate" to 2 decimal places and other answers to the nearest whole dollar amount.)
Using activity-based costing, compute the overhead cost per unit for each model. (Round "Activity Rate" to 2 decimal places and other answers to the nearest whole dollar amount.)
|
Compute the total product cost per unit for each model. (Do not round intermediate calculations.)
|
For each model, compute the gross profit per unit (selling price per unit minus product cost per unit). (Do not round intermediate calculations. Negative amounts should be indicated with a minus sign.)
|
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started