Identify an accurate statement about the PERT (program evaluation and review technique) chart. Group of answer choices It was first developed by Henry Gantt. It
Identify an accurate statement about the PERT (program evaluation and review technique) chart. Group of answer choices It was first developed by Henry Gantt. It focuses on the shortest path taken to complete an activity rather the critical path. It indicates the most optimistic estimates of the time to complete a project under the best conditions. It maps tasks exclusively in line and bar graphs
Step by Step Solution
There are 3 Steps involved in it
Step: 1