: If a company had the following standards: Materials 2kgs @$4 per kg Labour 4 hours @$25 per hour Purchased 8000 kgs for $32,800 Made
: If a company had the following standards:
Materials 2kgs @$4 per kg
Labour 4 hours @$25 per hour
Purchased 8000 kgs for $32,800
Made 2000 units
Actual material used was 4300 kgs
Actual labour time and cost was 7900 hours with labour cost of $202,240
Calculate: DMPV = PQ x (AP - SP)
DMQV = SP x (AQ - SQ*) SQ for 2000 units produced!!!!
DLRV = AH x (AR - SR)
DLEV = SR x (AH - SH*) SH for 2000 units produced!!!!