If a delay in an activity will delay completion of the whole project, the activity Select answer from the options below is a dummy. is
If a delay in an activity will delay completion of the whole project, the activity
Select answer from the options below
is a dummy.
is represented by a node.
is on the critical path.
has slack.
is costly