If a risk breakdown structure (RBS) had been constructed for the Challenger event, which component of the RBS would reflect the influences demonstrated in this
If a risk breakdown structure (RBS) had been constructed for the Challenger event, which component of the RBS would reflect the influences demonstrated in this case: human interactions, dysfunctional behavior, and conflict? Question 6 options: Technical Adminstrative/Project Management Organizational External