If a task has a Finish slack day of 10 days, this means that: Group of answer choices The task can finish up to 10

If a task has a Finish slack day of 10 days, this means that: Group of answer choices The task can finish up to 10 days late without affecting the project Finish date The task should finish 10 days early so that it does not affect the project Finish date The task is critical and cannot finish late The task has to start 10 days before the last project task

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Information Systems Managing the Digital Firm

Authors: Kenneth C. Laudon, Jane P. Laudon, Mary Elizabeth Brabston

7th Canadian edition

133156842, 9780133577099 , 978-0133156843

More Books

Students also viewed these General Management questions

Question

=+c) How many baseballs produced were out of spec?

Answered: 1 week ago

Question

1. To generate a discussion on the concept of roles

Answered: 1 week ago