If a WP with a TF=4 days start with a delay of 4 days, what happens: a. The WP becomes critical b. The WP still
- If a WP with a TF=4 days start with a delay of 4 days, what happens:
a. The WP becomes critical
b. The WP still have a TF=4
c. The project end date changes, generating a delay equal to 4 days
d. Nothing significant