If a WP with a TF=4 days start with a delay of 4 days, what happens: a. The WP becomes critical b. The WP still

  1. If a WP with a TF=4 days start with a delay of 4 days, what happens:

a. The WP becomes critical

b. The WP still have a TF=4

c. The project end date changes, generating a delay equal to 4 days

d. Nothing significant

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Principles Of Financial Accounting

Authors: Kermit Larson, John Wild

20th Edition

77338235, 978-0077619442

More Books

Students also viewed these Accounting questions

Question

Explain all drawbacks of the application procedure.

Answered: 1 week ago

Question

Determine Leading or Lagging Power Factor in Python.

Answered: 1 week ago