If (Activity, Optimistic, Most likely, Pessimistic, Dependency) for the activities are given as follows (A, 1,3,5,-), (B, 2, 4, 6, A), (C, 4, 6, 8,
If (Activity, Optimistic, Most likely, Pessimistic, Dependency) for the activities are given as follows (A, 1,3,5,-), (B, 2, 4, 6, A), (C, 4, 6, 8, A), (D, 1, 2, 3, B and C), what is slack time for activity B a. Slack time = 3 b. Slack time = 2 c. Slack time = 0 d. Slack time = 1