If actual project costs are consistently exceeding the cost baseline because the proposal team was too aggressive with their cost estimates, the best corrective action
If actual project costs are consistently exceeding the cost baseline because the proposal team was too aggressive with their cost estimates, the best corrective action for the project team is Group of answer choices To improve project performance to match the cost baseline To modify the cost baseline to be more realistic To replace the proposal team To notify the customer of the