If an activity can be completed in 10 weeks at a cost of $3,200 instead of the normal time of 12 weeks at a cost
If an activity can be completed in 10 weeks at a cost of $3,200 instead of the normal time of 12 weeks at a cost of $2,400, then the crash cost per week for the given activity is _____. Group of answe