If an activity has 64 budgeted labor units and the project is working on 4-10 work schedule. What is the duration of this activity? Select
If an activity has 64 budgeted labor units and the project is working on 4-10 work schedule. What is the duration of this activity? Select one: a. 64 Days b. 6 Days c. None of the Above d. 7 Days