If an activity whose normal duration is 15 days can be shortened to 11 days for an added cost of $2,000, the crash cost per
If an activity whose normal duration is 15 days can be shortened to 11 days for an added cost of $2,000, the crash cost per period is . $10000 O b. $400 O c. $20000 O d. $500 O e. $30000