If BCWS (budgeted cost of work scheduled) is > BCWP (budgeted cost of work performed), at a particular point in the project, what can you
If BCWS (budgeted cost of work scheduled) is > BCWP (budgeted cost of work performed), at a particular point in the project, what can you say about the project at that point? Group of answer choices The project is over budget The project is on schedule The project is ahead of schedule The project is under budget The project is behind shedule The project is on budget