If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then

If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good
LF=LS+D
LS=LF-D
All
D=EF-ES
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

OM operations management

Authors: David Alan Collier, James R. Evans

5th edition

1285451376, 978-1285451374

More Books

Students also viewed these General Management questions

Question

Design a continuous or periodic review inventory-control system.

Answered: 1 week ago