If either project 3 or project 6 is selected, then project 8 must be selected. For integer programming problems, which one of the alternatives listed

If either project 3 or project 6 is selected, then project 8 must be selected.

For integer programming problems, which one of the alternatives listed below correctly models this situation?

a. x3 + x6 + x8 1

b. x3 - x8 1, x6 - x8 1

c. x3 + x8 1, x6 + x8 1

d. x6 x8 , x3 x8

e. None of the above