If estimated factory overhead cost is $35,000 and activity base is estimated at 5,000 direct labor hours. What is the predetermined overhead rate? Select one:
If estimated factory overhead cost is $35,000 and activity base is estimated at 5,000 direct labor hours. What is the predetermined overhead rate?
Select one:
A. $5
B. $4
C. $6
D. $7