If it becomes necessary to delay one or several late starts to accommodate resource limitations , this is called: Splitting Resource - constrained scheduling Resource
If it becomes necessary to delay one or several late starts to accommodate resource limitations this is called:
Splitting
Resourceconstrained scheduling
Resource smoothing
Resource scheduling
Resource accommodation