If the budget of a project is Rs 1,00,000, a total of 3,00,000 has been spent already and 20% work is completed against a target
If the budget of a project is Rs 1,00,000, a total of 3,00,000 has been spent already and 20% work is completed against a target of 40%,
A. CPI < 1 and SPI > 1
B. CPI > 1 and SPI > 1
C. CPI < 1 and SPI < 1
D. CPI > 1 and SPI < 1