If the cost variance and the schedule variance have values greater than zero, then the project Select the single best answer: A. is under budget
If the cost variance and the schedule variance have values greater than zero, then the project
Select the single best answer:
A. is under budget and ahead of schedule
B. is over budget and ahead of schedule
C. is over budget and behind schedule
D. is under budget and behind schedule
E. needs a new project scope statement