If the Earned Value Management ( EVM ) data for Project B is as follows: Latest Revised Estimate ( LRE ) = 9 , 5

If the Earned Value Management (EVM) data for Project B is as follows:
Latest Revised Estimate (LRE)=9,500
Actual Cost of Work Performed (ACWP)=3,800
Budget At Completion (BAC)=6,445
Budgeted Cost of Work Performed (BCWP)=3,300
Budgeted Cost of Work Scheduled (BCWS)=4,250
Then a Three-Point Estimate for Project B would be:

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Successful Time Management

Authors: Patrick Forsyth

6th Edition

1398606197, 978-1398606197

More Books

Students also viewed these General Management questions

Question

Determine if gender differences in PTSD exist.

Answered: 1 week ago

Question

Write a program to check an input year is leap or not.

Answered: 1 week ago

Question

Write short notes on departmentation.

Answered: 1 week ago

Question

What are the factors affecting organisation structure?

Answered: 1 week ago

Question

What are the features of Management?

Answered: 1 week ago

Question

Briefly explain the advantages of 'Management by Objectives'

Answered: 1 week ago